Afrimat business update and pre-close briefing session
AFRIMAT LIMITED
Incorporated in the Republic of South Africa
(Registration number: 2006/022534/06)
Share code: AFT
ISIN: ZAE000086302
("Afrimat" or "the Company")
AFRIMAT BUSINESS UPDATE AND PRE-CLOSE BRIEFING SESSION
Background
The build-up to the first half of the 2025 financial year ("HY2025") is best characterised by two
distinct quarters. In the first quarter (March, April, May) ("Q1") the bulk commodity market was
lacklustre. The continued underperformance of the iron ore export corridor, together with
ArcelorMittal South Africa Limited's ("ArcelorMittal") well-documented issues (specifically
the force majeure being declared at the Vanderbijlpark facilities due to the freeze of two
furnaces), impacted Afrimat volumes in Q1.
By the second quarter (June, July and the first week of August) ("Q2"), volume increases were
evident, as domestic customers with furnaces started up again, and tender activity increased
in road, rail and small infrastructure projects. However, the increase in volumes in Q2 is not
sufficient to make up for the volume decline in Q1.
Construction Materials
Volume levels across the segment were maintained in Q1. By Q2, the integrated Lafarge
quarries increased volumes. Afrimat is thrilled to announce that our ethos of job creation and
economic empowerment continues with 34 new appointments in the Lafarge business of which
25 are fixed-term contracts, 5 are permanent and 4 learners were taken on.
The loss-making cement component in the Lafarge business has been reduced but remains
loss-making at this point in time. At the time of the acquisition, the cement kilns were extremely
unreliable, and a highly experienced team is working on the turnaround. Although an
improvement is already visible, this business component is expected to remain loss-making
by the end of Q2. Innovative strategic initiatives are expected to turn this business unit into a
good contributor in future.
Industrial Minerals
The suspension of loadshedding is positive for both the segment and its customers. Starting
from a low baseline, the volume increase is encouraging and was further supplemented
through strategic marketing initiatives into new markets.
Bulk Commodities
Afrimat remains encouraged by Transnet's new management team's cooperation. However,
the limited availability of locomotives, derailments and maintenance downtime at Transnet
continue to constrain the performance of export iron ore. The HY2025 volumes are down by
20% when compared against the HY2024 volumes. The international iron ore price, which has
remained in a low trading band, remains attractive to Afrimat, which has positioned itself as a
low-cost operator.
Local iron ore volumes suffered a 70% retraction in Q1. This was due to significantly reduced
volumes taken by ArcelorMittal. Pleasingly, volumes for Q2 began increasing and are tracking
at normal levels, correlating with ArcelorMittal's business update and trading statement
released on 2 July 2024. Afrimat expects volumes to ArcelorMittal to return to normal ranges
for the remainder of the financial year.
At the Nkomati Anthracite Mine, the production rate at the open pits have been ramped up.
An Eskom powerline is being moved after a frustratingly long approval time, further enhancing
the ease of the open cast mining operations. Afrimat continues to find underground operations
difficult due to geological limitations.
Future Materials and Metals
With the single super phosphate plant commissioned, sales volumes for fertiliser are coming
through and ramped up to achieve the planned volumes of 30 000 tons by 2025, which will
then contribute positively to the 2026 financial year. The rare earth component continues to
be diligently researched.
Looking forward to the second half of FY2025 ("HY2")
The suspension of loadshedding and the established Government of National Unity have had
a positive effect on Afrimat and its customers. Afrimat and its subsidiaries ("the Group") hopes
that the political parties will collaborate, focusing on critical projects, initiatives and
maintenance to ensure infrastructure is maintained and economic growth is achieved.
Afrimat continues to engage with Transnet and participates in the Ore User's Forum to assist
Transnet as much as possible.
In HY2, Afrimat is expecting to dispatch at least 3 shipments of export anthracite in addition to
normal local sales.
The Group is satisfied with the steady progress being made in respect of the Lafarge
integration. The team's successful mitigation of losses in certain operations is a testament to
our confidence in this strategic acquisition, an essential component of Afrimat's ongoing
diversification.
Pre-close briefing session
Afrimat shareholders are advised that the Company will host a pre-close briefing session
relating to its business activities for the period ended 31 August 2024 and provide feedback
on the first 100 days of the Lafarge integration via a virtual discussion from 11:00 to 12:00 on
Friday, 23 August 2024.
Shareholders interested in attending the briefing session should contact Keyter Rech Investor
Solutions at antoinette@kris.co.za for the link.
A recording of the session can be requested by contacting Keyter Rech Investor Solutions at
the abovementioned email address.
Further update
Afrimat will update the market in September 2024 once management has greater certainty on
the financial position.
This announcement contains forward-looking statements based on the Group's current beliefs
and expectations of future events. The financial information contained in this announcement
has not been reviewed by the Group's external auditors.
Cape Town
6 August 2024
Sponsor
Valeo Capital (Pty) Ltd
Date: 06-08-2024 07:15:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.