Operational and Production Update 9m FY2026
Jubilee Metals Group Plc
Registration number (4459850)
AIM share code: JLP
Altx share code: JBL
ISIN: GB0031852162
('Jubilee' or 'Company' or 'Group')
Dissemination of a Regulatory Announcement that contains inside information according to UK
Market Abuse Regulations. Not for release, publication or distribution in whole or in part in, into or
from any jurisdiction where to do so would constitute a violation of the relevant laws or regulations
of such jurisdiction.
Operational and Production Update 9m FY2026
Jubilee, the integrated copper producer and resource developer in Zambia, today publishes its
operational and production update for the nine-month period ended 31 March 2026 ('9m FY2026' or
'the period').
Highlights
• Lost Time Frequency Injury Rate (LTFIR) of 0.00 for the period (FY2025: 1.40)
• Total saleable Cu production for the period increased by 28.7% to 2 177t (9m FY2025: 1 691t) *
o Roan production increased to 1 999t of copper ('Cu') units for the period, a 112.7%
increase from the comparative period a year earlier
- Roan produced 779t Cu units in oxide concentrate fines for the period
(production of Cu units in oxide concentrate fines only commenced in August
2025)
o Sable Refinery production totalled 957t of Cu cathodes for the period (9m FY2025: 751t)
• Commissioning of the expanded Roan Cu concentrate facility is near completion with the ramp-
up of dewatered fine Cu concentrate production underway during May 2026. The circuit is
currently operating at approximately 75% of the targeted production rate of 110-120tpm of
contained Cu
o The dewatering circuit has a design capacity of approximately 230tpm of contained Cu,
enabling the simultaneous processing of the historical stockpile (14 000t) and additional
production of fine Cu concentrate at a rate of 110-120tpm of Cu
• Molefe Mine operations continue to expand, with 250 162t of ore mined during the period, (181
890t for H1 FY2026), of which 20 064t (9 130t for H1 FY2026) were transported to Sable Refinery
at an average Cu grade of 1.84%
• Implementation of the near term mine plan at Molefe Mine is underway (see 31 March 2026
announcement)
o Accelerated stripping programme to expand Pits 2 and 3 into a single open-pit mine
progressing to plan and expected to be fully completed by July 2026
o During April 2026, more than 250 000t of pre-stripping material was removed as part of
the stripping programme which will support significant increased delivery of Cu ROM to
the Sable Refinery once completed
* Excludes the stockpiled Cu fine concentrate at Roan as well as the stockpiled Molefe mined material
Q1 Q2 Q3 9m to 31 9m to 31 %
PRODUCTION PERFORMANCE
FY2026 FY2026 FY2026 Mar 2026 Mar 2025 change
Roan production*
Cu units in oxide
tonnes 83 155 160 398 84 373.8%
concentrates
Cu units in sulphide
tonnes 639 70 113 822 856 (4.0%)
concentrates
Cu units in oxide
tonnes 152 330 297 779 - -
concentrate fines
Total Roan production tonnes 874 555 570 1 999 940 112.4%
Sable Refinery production
Cu cathodes tonnes 217 379 361 957 751 27.4%
Total saleable Cu units
produced ** tonnes 939 604 634 2 177 1 691 28.7%
Molefe Mine production
Cu reef ore mined tonnes 38 648 143 242 68 272 250 162 - -
Ore dispatched to Sable
Refinery tonnes 881 8 249 10 934 20 064 - -
* Cu tonnes produced comprises three streams:
o Cu in oxide concentrate that is further refined to cathode at Sable Refinery
o Cu in sulphide concentrate which is sold directly into the market
o Cu in the oxide concentrate fines which are currently stockpiled and will be processed by the recently commissioned
dewatering facility at Roan, before being delivered to Sable Refinery for further refining
** Includes Cu cathode produced at Sable Refinery and Cu sulphide concentrate produced at Roan and excludes all
Cu units in oxide concentrate fines stockpiled at Roan
Copper production guidance for FY2026
Copper production guidance for FY2026 is under review based mainly on:
o The updated Molefe Mine plan following the completion of the phase 1 drilling
programme which informed the fast tracking of the expanded stripping programme to
further enlarge Pits 2 and 3 into a single large open-pit which is currently underway and
expected to be completed by July 2026; and
o The short delay in the commissioning and ramp-up of the expanded concentrate
dewatering circuit at Roan which delayed the step -up of the expected additional 110t
of equivalent Cu units from Roan. Commissioning is near completion, with ramp-up
expected to reach targeted production during May 2026.
The Company expects to provide a further update on guidance following confirmation by the contracted
consulting firm of progress with the expansion programme at Molefe Mine as well as the expanded
concentrate dewatering circuit reaching steady-state operation, which is anticipated within the coming
weeks.
Statement from Leon Coetzer, Jubilee CEO:
"We continue to make strong progress in delivering our Zambia copper strategy, with Roan sustaining
targeted production rates and the expanded concentrate circuit now entering ramp-up after minor
technical and logistical delays, marking a key step-change in our processing capability. Our focus remains
firmly on disciplined, milestone-driven execution.
At Molefe Mine, continued operational expansion, supported by encouraging drilling results, highlights
the strength of our transition towards a resource-backed copper producer. While heavy rains impacted
the quarter, momentum remains strong as we advance the mine plan and plan increased production.
Importantly, the Company continues to produce while building a scalable resource base, positioning
Jubilee to deliver both near-term returns and long-term value. This integrated approach gives us strong
confidence in delivering sustained and scalable growth in copper production."
Overview
The implementation of the Company's Three-Pillar copper strategy continues to progress on track, with
Roan achieving and sustaining its targeted production levels, while Molefe Mine continues to expand,
supported by encouraging early results from its resource drilling programme.
Pillar 1 - Processing of third-party copper feedstock: Roan
Production at Roan reached 1 999t of Cu units during the period, up 112.7% on the previous comparable
period. Production at Roan comprises three streams, namely, Cu in oxide concentrates - 398t for the
period (238t in H1 FY2026) for further refining at Sable Refinery, Cu sulphide concentrates - 822t (709t
in H1 FY2026) for direct sale, and Cu in oxide concentrates fines - 779t (482t in H1 FY2026) which are
stockpiled for future refining at Sable Refinery.
Production of dewatered Cu concentrate has also commenced at the newly expanded Cu concentrate
dewatering facility. Commissioning is near completion, with ramp-up scheduled to commence during
May 2026, following the resolution of minor technical and logistical factors. The circuit is currently
operating at approximately 75% of the targeted production rate of 110-120tpm of contained Cu. The
expansion increases dewatering capacity by approximately 30% and specifically targets the fine Cu
concentrates.
To date, fine Cu concentrate has been produced and stockpiled at Roan (c.14 000t), which post
dewatering, will be transported to the Sable Refinery for further processing into Cu cathode. This fine
Cu concentrate stream is in addition to the existing Cu oxide concentrate produced at Roan and currently
refined at Sable Refinery. Roan will commence with its scheduled annual maintenance on the 8th of May
2026. The Roan operations will be stopped during the scheduled 6-day maintenance period. The Sable
operations are expected to continue operating over this period as we reduce our built-up in process
stocks.
• Production Impact of New Dewatering Capacity
The addition of the fine Cu concentrate stream is expected to support incremental Cu production of
approximately 110-120tpm of Cu cathode. The dewatering circuit has a design capacity of approximately
230tpm of contained Cu, allowing for the simultaneous processing of:
- the historical stockpile of approximately 14 000t of fine Cu concentrate (at ~2.7% Cu), and
- ongoing production of fine Cu concentrate at a rate of 110-120tpm of Cu.
The Roan concentrator continues to operate at approximately 30 000tpm. The Roan front-end upgrade
offers the potential to increase the feed rate to in excess of 40 000tpm, which the Company looks to
bring back into operation following the end of the seasonal rains and the completion of the
commissioning and ramp-up of the new fine concentrate dewatering system.
Pillar 2 - Integrated mine-to-metals business: Sable Refinery and mining operations
At the Molefe Mine, the accelerated pre-stripping programme commenced in April 2026 and is on track
for completion during July 2026, to support increased sustained production and improved feed to the
Sable Refinery. Development work to integrate Pits 2 and 3 to a single enlarged open-pit has begun and
is progressing well. Removal of approximately 250 000t of pre-stripping material by the end of April 2026
supports the transition to increased ore delivery rates from Pit 2.
Upon completion of the pit integration and development programme, the mine is expected to ramp-up
from approximately 12 000t per quarter to in excess of 30 000t per quarter of Cu reef ore. The expansion
is underpinned by continued access to a widened Cu reef zone, supporting an expected average grade
of approximately 1.4% total Cu to surface, prior to the application of targeted ROM ore sorting.
High-grade material will be transported to the Sable Refinery for direct processing, with low-grade
material stockpiled for on-site upgrading and later refining.
Molefe Mine operations continue to expand with 250 162t of Cu reef mined during the period, of which
20 064t were transported to Sable Refinery at an average Cu grade of 1.84%. The remaining tonnes
continue to be stockpiled at Molefe Mine for future on-site processing prior to refining at Sable Refinery
already exceeding 2.3Mt.
Regarding the JORC resource, an independent third-party will compile a JORC-compliant resource
following completion of the Phase 2 drilling programme. Assay results from the first drilling campaign,
together with initial samples from the second campaign have been submitted to an independent
laboratory for analysis. The competent person's report is currently expected by Q4 CY2026, subject to
the timely receipt of assay results. Further drill campaigns will be considered following the completion
of and review of the competent person's report.
Molefe Presentation
Company intends to host a presentation on the Molefe Mine during June 2026. The timing reflects
ongoing work at site, where our JV partner is currently reviewing the next phase of stripping and future
mining strategy. This review, incorporating the results from the initial drilling programme and the
completed portion of the second phase, is expected to conclude within the coming weeks, allowing the
Company to present a clear and aligned development plan.
South African Head Office Relocation
The Company expects to relocate its South African Head Office in early June 2026. The relocation reflects
a right-sizing of office space following the disposal of its South African chrome and PGM operations. The
new Head Office address will be Southdowns Ridge Office Park, Ground Floor, Suite 04, corner John
Vorster and Nellmapius Drive, Irene, 0157.
6 May 2026
For further information visit www.jubileemetalsgroup.com, follow Jubilee on X (@Jubilee_Metals) or
contact:
Jubilee Metals Group PLC
Leon Coetzer (CEO)/Jonathan Morley-Kirk (FD)
Tel: +27 (0) 11 465 1913 / Tel: +44 (0) 7797 775546
Nominated Adviser - SPARK Advisory Partners Limited
Andrew Emmott/James Keeshan
Tel: +44 (0) 20 3368 3555
PR & IR Adviser - Tavistock
Jos Simson/Gareth Tredway
Tel: +44 (0) 207 920 3150
Joint Broker - Zeus Capital
Harry Ansell/Katy Mitchell
Tel: +44 (0) 20 7220 1670/+44 (0) 113 394 6618
Joint Broker - Shard Capital Partners LLP
Erik Woolgar/Gareth Burchell
Tel +44 (0) 207 1869900
JSE Sponsor - Questco Corporate Advisory Proprietary Limited
Alison McLaren
Tel: +27 63 482 3802
About Jubilee Metals Group
Jubilee Metals, listed on AIM and the Altx of the JSE, is a copper producer focused on building a world-
class integrated copper business in Zambia. The Company aims to reach 25 000 tonnes per annum of
copper production by integrating exploration, mining, concentrating and refining through its three-pillar
strategy, combining the Roan concentrator, the Sable refinery and regional mining assets and the Large
Waste Rock Project. Led by an experienced team, Jubilee applies innovative technologies to transform
previously underutilised materials into value while supporting circular resource use and strong
environmental stewardship.
For further information, please visit www.jubileemetalsgroup.com and follow Jubilee on X at
@Jubilee_Metals
Date: 06-05-2026 08:00:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.